New York Construction Site Safety Code
PART 23
PROTECTION IN CONSTRUCTION, DEMOLITION
AND EXCAVATION OPERATIONS
(Statutory authority: Labor Law, §§27-a,
27, 29)
SUBPART 23-2 CONSTRUCTION OPERATIONS
23-2.1
Maintenance and
housekeeping
23-2.2
Concrete work
23-2.3
Structural steel
assembly
23-2.4
Flooring
requirements in building construction
23-2.5
Protection of
persons in shafts
23-2.6
Catch platforms
required
23-2.7
Stairway
requirements during the construction of
buildings
23-2.8
Painting
SUBPART
23-2
CONSTRUCTIONS OPERATIONS
Historical Note
Subpart (§§23-2.1 - 23-2.8) added, filed
May 30, 1972 eff. June 1, 1972.
Top^
§ 23-2.1 Maintenance and housekeeping.
(a) Storage of material or equipment.
(1) All building materials shall be
stored in a safe and orderly manner.
Material piles shall be stable under all
conditions and so located that they do
not obstruct any passageway, walkway,
stairway or other thoroughfare.
(2) Material and equipment shall not be
stored upon any floor, platform or
scaffold in such quantity or of such
weight as to exceed the safe carrying
capacity of such floor, platform or
scaffold. Material and equipment shall
not be placed or stored so close to any
edge of a floor, platform or scaffold as
to endanger any person beneath such
edge.
(b) Disposal of debris. Debris shall be
handled and disposed of by methods that
will not endanger any person employed in
the area of such disposal or any person
lawfully frequenting such area.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
(a) General requirements. Forms,
shores and reshores shall be
structurally safe and shall be properly
braced or tied together so as to
maintain position and shape.
(b) Inspection. Designated persons shall
continuously inspect the stability of
all forms, shores and reshores including
all braces and other supports during the
placing of concrete. Any unsafe
condition shall be remedied immediately.
(c) Beams, floors and roofs. (1)
Necessary horizontal and diagonal
bracing shall be provided in both
longitudinal and transverse directions
to provide structural stability of
beams, floors and roofs. Shores and
reshores shall be properly seated top
and bottom and shall be secured in
place.
(2) Where shores or reshores rest upon
the ground, mud sills or other bases
shall be provided.
(3) Where the sum of the dead and live
loads on the forms may exceed 150 pounds
per square foot, the design of such
forms, including shores, reshores and
bracing, shall be as specified by a
professional engineer licensed to
practice in the State of New York. Such
design plans and specifications shall be
kept on the job site available for
examination by the commissioner. All
forms, shores, reshores and bracing
shall be constructed and installed in
accordance with such design plans and
specifications.
(d) Stripping. After stripping, forms
shall be promptly stockpiled or removed
from areas in which persons are required
to work or pass. Protruding nails, wire
ties and other form accessories not
necessary for subsequent work shall be
pulled, cut or otherwise made safe.
(e) Reshoring. Reshoring shall be
provided when necessary to safely
support slabs and beams after stripping
or where such members are subjected to
superimposed loads due to construction
on upper levels.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-2.3 Structural steel assembly.
(a) Placing of structural members.
(1) During the final placing of
structural steel members, loads shall
not be released from hoisting ropes
until such members are securely fastened
in place. Structural steel members shall
not be forced into place by hoisting
machines while any person is so located
that he may be injured thereby.
(2) Open web steel joists that are
hoisted singly shall be transferred from
their place of storage directly to their
permanent location and secured against
dislodgment. Such a load shall not be
released from the hoisting rope until it
is so secured. Bundles of such joists
shall be so placed as to prevent
accidental dislodgment while being
hoisted. Immediately upon the release of
the ties or straps from such bundles,
the individual joists shall be
distributed to and placed in their
permanent positions and secured against
accidental dislodgment.
(3) Loads shall not be placed on open
web steel joists until such joists are
permanently located and secured
including the installation of required
bridging.
(b) Holing or cutting of structural
steel members. Load-bearing structural
steel members shall not be materially
weakened by holing, cutting or by any
other means except in accordance with
the advice of the designer thereof or of
a professional engineer licensed to
practice in the State of New York.
(c) Tag lines. While steel panels or
structural steel members are being
hoisted, tag lines shall be provided and
used to prevent uncontrolled movement of
such panels or members.
(d) Erection of lintels. Where exterior
metal lintels are erected in steel or
concrete frame buildings or other
structures after the permanent floors
have been installed, a suitable scaffold
constructed and installed in compliance
with this Part (rule) shall be provided
and used unless each person engaged in
the work of erecting such lintels is
provided with and wears an approved
safety belt or harness in compliance
with this Part (rule).
(e) Tandem loads. The suspension of
tandem loads from the boom or hook of
any crane or derrick over any area or
location where persons work or pass is
prohibited.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-2.4 Flooring requirements in building construction.
(a) Permanent flooring – skeleton
steel construction in tiered buildings.
The permanent floors of such buildings
or other structures shall be installed
as soon as possible as the erection of
structural steel members progresses. In
no case shall there be more than eight
stories, floors or equivalent levels or
120 feet, whichever is less, between the
erection floor and the uppermost
permanent floor.
(b) Temporary flooring – skeleton steel
construction in tiered buildings. (1)
Erection by tower crane or derrick.
(i) The erection floor shall be covered
over the entire surface except for
access openings. Such flooring shall be
of the proper strength to support the
working load intended to be imposed
thereon. Such temporary flooring shall
be laid tight and secured against
movement.
(ii) There shall also be provided a
tight and substantial floor within two
stories or 30 feet, whichever is less,
below and directly under that portion of
each tier of beams on which any work is
being performed. Such floor shall be of
the proper strength to support the
working load intended to be imposed
thereon. Such floor shall be constructed
of planking at least two inches thick
full size or material of equivalent
strength as a minimum.
(2) Erection by ground-supported crane.
Where erection is being done by means of
a crane operating on the ground, grade
or equivalent surface, a tight, secure
and substantial floor shall be installed
within two stories or 30 feet, whichever
is less, below and directly under that
portion of each tier of beams on which
any work is being performed. Such floor
shall consist of planking at least two
inches thick full size or of material of
equivalent strength. As an alternative
to such floor, an approved life net
installed in compliance with this Part
(rule) may be provided. Any such life
net shall be installed and maintained
not more than two stories or 30 feet,
whichever is less, below and directly
under that portion of each tier of beams
on which any work is being performed.
(3) High one story skeleton steel
construction. In the erection of one
story skeleton steel buildings or other
structures where the clear vertical
height of such building or other
structure is 30 feet or more, protection
similar to that required for tiered
construction as specified in paragraphs
(1) and (2) above shall be provided.
(c) Flooring – other construction. (1)
In the erection of any building or other
structure having double wood floor or
bar joist construction, the rough
flooring shall be completed as the
construction of such building or other
structure progresses, including the tier
below the one on which the wood floor
joists or bar joists are being
installed.
(2) In the construction of a building or
other structure having single wood
flooring or any other flooring system,
the floor immediately below the story
where the floor joists are being
installed shall be kept covered. Such
flooring shall be at least two inches
thick full size or shall be of material
of equivalent strength and be laid tight
and secure.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-2.5 Protection of persons in shafts.
(a) General. Persons required to
perform work in or at shafts, other than
elevator shafts, shall be provided with
the following protection:
(1) Protection from falling material. A
tight covering consisting of planks at
least two inches thick full size,
exterior grade plywood at least
three-quarters inch thick or material of
equivalent strength shall be installed
so as to cover the entire
cross-sectional area of the shaft. Such
cover shall be located at a point in the
shaft not more than two stories or 30
feet, whichever is less, above the level
where persons are working.
(2) Protection from falling. (i) To
minimize injuries from falls in shafts,
a tight platform consisting of planks at
least two inches thick full size,
exterior grade plywood at least
three-quarters inch thick or material of
equivalent strength shall be installed
not more than one story or 15 feet,
whichever is less, in the shaft below
the level where persons are working. In
lieu of such platform, an approved life
net installed in compliance with this
Part (rule) may be provided. Such
approved life net shall be installed in
the shaft not more than one story or 15
feet, whichever is less, below the level
where persons are working.
(ii) In buildings or other structures
where stair halls, stairwells or other
similar shafts are to be constructed of
masonry, floor slab forms or planking at
least two inches thick full size shall
be installed as the work progresses.
Such slab forms or planking shall be
installed in such shafts not more than
two stories or 30 feet, whichever is
less, below the story on which any
brickwork or masonry is being erected.
(b) Protection of persons in elevator
shafts. (1) During the installation,
repair or replacement of any elevator
where persons are working in the
elevator shaft, except for the stacking
of elevator rails, a tight platform
consisting of planks at least two inches
thick full size, exterior grade plywood
at least three-quarters inch thick or
material of equivalent strength shall be
installed not more than two stories or
30 feet, whichever is less, above the
level at which any work is being
performed so as to provide protection
against falling objects or material.
Such platform shall cover the entire
cross-sectional area of the shaft except
that spaces not exceeding 12 inches may
be left for rail clearance between the
edge of the platform and the sides of
the shaft. Protection for persons
stacking elevator rails shall be
provided by the installation of a
platform as described above which shall
be installed immediately above the hitch
point of the hoisting equipment.
(2) A similar platform such as is
specified in paragraph (1) above shall
be installed level with the top landing
of each elevator shaft in which work is
being performed to prevent any person
from falling into such shaft.
(3) Where any elevator is being
installed, repaired or replaced and
persons are working in the shaft, a
solid or wire mesh partition shall be
provided where necessary to prevent such
persons from contacting any adjacent
operable elevator or counterweight.
(4) Where persons are required to
perform any work at intermediate levels
between stories in elevator shafts, such
persons shall be provided with overhead
protection from falling objects or
material. Such protection shall be at
least 27 inches in width and shall cover
the area where the persons are working.
(5) Where persons are required to
perform any work at intermediate levels
between stories in an elevator shaft,
such persons shall be provided with
protection against falling. Such
protection shall be either an approved
life net installed in compliance with
this Part (rule) or planking at least
two inches thick full size or other
material of equivalent strength. Such
protection shall be located not more
than two stories or 30 feet, whichever
is less, below the point in the elevator
shaft where such persons are working. In
lieu of an approved life net or
substantial covering, such persons may
use approved safety belts or harnesses
securely attached to hanging lifelines
in compliance with this Part (rule).
(6) While any work is being performed in
existing elevator shafts, all shaft
doors shall be kept closed except where
it is necessary to keep a door open in
order to perform the work in which case
either the elevator car shall be locked
at such landing and a chain or other
barrier between 36 and 42 inches in
height shall be placed across the door
opening, or a person shall be stationed
at such door opening to prevent
unauthorized entrance to such door
opening.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-2.6 Catch platforms required.
(a) During the construction of
exterior masonry walls of any building
or other structure, except chimneys,
from a floor or scaffold inside the
building or other structure and such
floor or scaffold is more than 35 feet
above the adjoining ground or equivalent
surface, there shall be provided along
the exterior face of such wall a catch
platform, installed in compliance with
this Part (rule) with the following
exceptions:
(1) In lieu of the required barricade or
fence on all open sides of the catch
platform, such sides shall be provided
with planks whose minimum
cross-sectional dimensions shall be two
inches by nine inches or material of
equivalent strength having one dimension
at least nine inches. Such planks or
material of equivalent strength shall be
so placed that the greater dimensions
are vertical.
(2) A two-inch space may be left between
the inner edge of the catch platform and
the face of the wall of the building or
other structure.
(b) Such catch platform shall be located
not more than 20 feet below the floor or
scaffold platform from which the work is
being performed.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
§ 23-2.7 Stairway requirements during the construction of buildings.
(a) General requirements. During the
construction of any reinforced concrete
building or other structure, at least
one stairway shall be installed which
shall extend to a level not more than
four floors or 60 feet, whichever is
less, below the uppermost working floor
or level. During the construction of
other types of buildings or other
structures, at least one stairway shall
be installed which extends to a level
not more than two floors or 30 feet,
whichever is less, below the uppermost
working floor or level. Such stairways
shall be extended upward as the
construction progresses to comply with
this Part (rule).
(b) Stairway construction. Temporary
stairways shall have treads constructed
of wood planks not less than two inches
by 10 inches in size, or metal not less
than two inches in depth of equivalent
strength. Such temporary stairways shall
be not less than three feet in width and
shall be substantially constructed and
rigidly braced. Such stairways more than
five feet in width shall be provided
with intermediate or center stringers.
Stairways with steel treads and landings
which are to be subsequently filled in
with concrete or provided with other
permanent tread surfacing shall be
provided temporary wooden treads
carefully fitted in place and extending
to the edges of the metal nosing and
over the full width of the treads and
landings.
(c) Skeleton iron or steel stairs.
Skeleton iron or steel stairs shall have
treads of wood planking not less than
two inches by 10 inches in size.
(d) Vertical rise. Any temporary
stairway shall not have a vertical rise
of more than 12 feet between landings or
floors.
(e) Protective railings. The stairwells
of temporary wooden stairways and of
permanent stairways where enclosures or
guard rails have not been erected shall
be provided with a safety railing
constructed and installed in compliance
with this Part (rule) on every open
side. Every stairway and landing shall
be provided with handrails not less than
30 inches nor more than 40 inches in
height, measured vertically from the
nose of the tread to the top of the
rail.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
(a) Confined space definition. As
used in this section, a confined space
means a room, a portion of a room or an
enclosure having no means of natural
ventilation other than one entrance
opening and which room, portion of a
room or enclosure is of such dimensions
that a painter is required to work
inside such room, portion of a room or
enclosure. Such confined space may be a
tank, an elevator car, a compartment, a
closet, the upper area of a high ceiling
room or a similarly enclosed space.
(b) General requirements. The painting
of confined spaces, including the use of
coating materials, paint removers,
stains, solvents and abrasives, shall be
so performed as to prevent the
dissemination of such harmful materials
into the air where persons are located
in quantities tending to injure the
health of such persons.
(c) Paint spraying. Persons engaged in
paint spraying operations and persons in
such close proximity to such operations
that they are exposed to the spray mists
shall be provided with and shall use
approved respirators. Operators of paint
spraying equipment shall be provided
with and shall use protective oil,
grease or cream on the exposed parts of
their bodies. Where such work is
performed in tanks, vats and similar
enclosed vessels, protection in addition
to the required respirators shall be
provided by means of mechanical exhaust
ventilation.
(d) Brush work. Persons engaged in brush
painting with other than water-mixed
paints in confined spaces shall be
provided with approved respirators.
Where brush work is performed in tanks,
vats and similar enclosed vessels,
protection in addition to the required
respirators shall be provided by means
of mechanical ventilation.
(e) Coating removal. Where coating
removal is being performed with any
volatile solvent in a confined space,
protection in addition to approved
respirators shall be provided by means
of mechanical ventilation.
(f) Machine sanding. An approved
respirator shall be provided for, and
shall be worn by, any person operating a
sanding machine unless the sandpaper is
wetted with oil or water or the sanding
machine is provided with a dust
collector.
Historical Note
Sec. added, filed May 30, 1972 eff. June
1, 1972.
Top^
New York City Slip and Fall Attorneys
New York Accident Lawyers